PHASE II June - October 2024
Week 19 – July 22-26, 2024
This week has been all about plumbing for the two new bathrooms! It is complete! We are waiting for inspection before filling the trench.
Prep for sheetrock work is done and materials are staged.
This week has been all about plumbing for the two new bathrooms! It is complete! We are waiting for inspection before filling the trench.
Prep for sheetrock work is done and materials are staged.
Week 18 – July 15-19, 2024
Framing is done and plumbing for new restrooms in the southern gallery is underway. The plumbing requires some excavation and boring to get under the building. Next week, we should see the plumbing complete and the start of sheet rock on the walls.
Framing is done and plumbing for new restrooms in the southern gallery is underway. The plumbing requires some excavation and boring to get under the building. Next week, we should see the plumbing complete and the start of sheet rock on the walls.
Week 17 – July 8-12, 2024
Framing in process - the reconfigured southern gallery is really taking shape! Sheet rock for the walls and rough-in plumbing for the two new restrooms on the east end of the gallery are on the schedule for next week.
After 42 years in the same spot, the Fresnel lens was moved to its new forever home on the west end of the southern gallery. And the roll up door that was uncovered a couple of weeks ago has been removed and the hole it left reconstructed as an exterior wall.
Framing in process - the reconfigured southern gallery is really taking shape! Sheet rock for the walls and rough-in plumbing for the two new restrooms on the east end of the gallery are on the schedule for next week.
After 42 years in the same spot, the Fresnel lens was moved to its new forever home on the west end of the southern gallery. And the roll up door that was uncovered a couple of weeks ago has been removed and the hole it left reconstructed as an exterior wall.